October 2024
A strong and deep foundation is key, and we are halfway through “Phase 1” of 2 critical foundation phases! The new building will be built on a “pile foundation” - which is an intensive process where piles (steel columns) are driven down into the ground, creating a solid footing. For perspective, these piles are each 11.9 meters long - that’s the equivalent of 4 stories!
While this process is tedious and time consuming, it is crucial! We praise God for the construction and engineering teams who are working to lay a solid foundation for our new building!
While this process is tedious and time consuming, it is crucial! We praise God for the construction and engineering teams who are working to lay a solid foundation for our new building!
June 2024
The new foundation preparations are well underway.
25 February 2024
Our construction site was officially turned over to the main builders!
9 November 2023
Demolition has reached the ground floor.
30 October 2023
Demolition continues!
14 October 2023
Demolition began 6 October!
The 3rd floor has been demolished.
The 3rd floor has been demolished.
20 August 2023
Hoarding walls are complete.
All the propping preparation for demolition is complete.
All the propping preparation for demolition is complete.